Green Building Certification Timeline for Existing Buildings:
No Cost to Owner |
Step One: Decision Time |
- Owner and Project Management is Thinking of GREEN
- Basic Green Building Information Session by Green Expert
- Owner and Project Management Decided to GO GREEN
|
1 Week |
Step Two: Preparation Time |
- Pre-qualification Walkthrough of the Project by Green Expert
- Collect Basic Project Information (If Qualify)
- Prepare and Submit Detail Fee Proposal with USGBC Certification Cost Detail
- Acceptance of Fee Proposal and Appoint the Green Expert
|
1 Week |
1st Payment |
Step Three: Data and Information Collection Time |
- Information Session on Green Building Certification Process with Project Team
- Collection of Project Energy and Water Consumption Data and Other Information
|
2 Weeks |
Step Four: Analysis Time (GB Consultancy PHASE I) |
- Feasibility Study Survey by International Green Building Expert
- ASHRAE Level I Walkthrough Assessment
- Submission of Reports (Feasibility Study Report, ASHRAE Level I Walkthrough Assessment Report and LEED Matrix Report
- ASHARE Level II Energy Audit and Retro Commissioning and Report
- Activate the Green Building Consultancy PHASE II by Owner
|
6 Weeks |
2nd Payment |
Step Five: Analysis Time (GB Consultancy PHASE II) |
- Create and Submission of Detail Step by Step Implementations Plan
- Establish Performance and Certification Goal
- Capital Improvements: Budget & Schedule
|
4 Weeks |
3rd Payment |
Step Six: Implementation Time (GB Consultancy PHASEIII) |
- Implementation of No/Low Cost Measures
- Implementation of Mid Cost Measures
- Implementation of Capital Improvements and High Cost Measures
- Ongoing Commissioning
- ASHARE 62.1 Ventilation Requirements
- Implementation of all Policies and Programs
- Staff/Tenant/Vendor Training
- Documentations of all Implementations
- Pre-commissioning Meeting
|
12 Weeks |
4th Payment |
Step Seven: Monitoring Time (GB Consultancy PHASE IV) |
- Tracking Material Input
- Occupant/Tenant Survey
- Collection of After Implementations Energy and Water Consumption Data and Other Information
- Verify Performance and LEED Compliances (Third Party Commissioning/Audit)
|
52 Weeks |
5th Payment |
Step Eight: Submission Time (GB Consultancy PHASE V) |
- Preparation of LEED Submission Documents
- Review the Submittal Documents with Project Owner/Management
- Completion of LEED documentation work and submission to USGBC/GBCI
- Preparation and submission of queries raised by GBCI by LEED consultant
- Second review completion by GBCI
- Review of final GBCI result by client and acceptance of LEED score&Award of LEED certification
|
10 Weeks |
Green Building Certification Timeline for New Buildings and Interior
No Cost to Owner |
Step One: Decision Time |
- Owner and Project Management is Thinking of GREEN
- Basic Green Building Information Session by Green Expert
- Owner and Project Management Decided to GO GREEN
|
1 Week |
Step Two: Preparation Time |
- Green Expert Visit the Project Site
- Collect Basic Project Information (Proposed Owner Project Requirement)
- Prepare and Submit Detail Fee Proposal with Certification Cost Detail
- Acceptance of Fee Proposal and Appoint the Green Expert
- Consultant register with US Green Building Council for LEED certification
|
1 Week |
|
Step Three: Data and Information Collection Time (GB Consultancy PHASE I) |
- Information Session on Green Building Certification Process with Project Team
- Provide all the Green Building Guidelines to Project Team
- Complete LEED Score Card
- Explain Energy Modelling Information Templates
- Collect all Completed Templates along with Architectural Design, Drawings, Elevations, Section, Air Ventilation/ HVAC Design, Light Design and Plumbing Design.
|
4 Weeks |
|
Step Four: Analysis Time (GB Consultancy PHASE II) by LEED Consultant |
- Location and Site Studies
- Sun Path Analysis,
- Local Weather and Climatic Studies
- Building Form and Orientation Studies
- Envelope Optimization,
- HVAC and Lighting System Review
- IAQ Management Calculation
- Water Efficiency Studies and Strategies
- Building Energy Efficiency Studies
- Fenestration Analysis
- Wall Roof and Floor Assembly Optimization
- Lighting and Other Systems Analysis
- Day Lighting Simulation and Views Analysis
- Lighting Pollution Analysis and Simulation
- Renewable Energy Studies, Calculation and Options
- Energy Simulation and Analysis
- Perform Calculations for Selected Credits
|
4 Weeks |
Step Five: Report (Deliverables) Submittal by LEED Consultant |
- Feasibility Study Report
- LEED Matrix Report
- Day Light Simulation Report
- Energy Modelling Report
- All LEED Credits Calculations
|
2 Weeks |
|
Step Six: Implementation Time (GB Consultancy PHASE III) |
- Construction Procedure Explain and Provide all Construction Guidelines
- Train the Green Officer
- Provide Project Team with all Sample Documents, Draft and LEED Documents Tracker
- Project Construction Monitoring and Documentation
- Regular Project Visit
- Collection of all Required Documents
- Pre- Commissioning Meeting (at 80% Completion of Project)
- On-site Verification of LEED Credits Implementation
- Submittal of Pre-commissioning Report (Deliverables)
|
Construction Time
|
|
Step Seven: Submission Preparation (GB Consultancy PHASE IV) |
- Fundamental Commissioning and Report
- O & M Manuals & Systems Manual
- Enhanced Commissioning and Report
- Preparation of LEED Submission Documents
- Review the Submittal Documents with Project Owner/Management
|
8 Weeks |
|
Step Eight: Submission (GB Consultancy PHASE V) |
- Completion of LEED documentation work and submission to USGBC/GBCI
- Preparation and submission of queries raised by GBCI by LEED consultant
- Second review completion by GBCI
- Review of final GBCI result by client and acceptance of LEED score
- Award of LEED certification and plaque from GBCI
|
10 Weeks |
|